Turn Key execution for the realization of a plant for the sinthesys and recovery of an inorganic chemical compound. Plant is composed by 1.000 mc reaction units and section for recovery composed by rotary vacuum filters, spin flash dryer, mills, filters, packing machines. Execution included mechanical eletrical instrumental civil HVAC works.
Multiproduct centrifugation department with nr. 2 Horizontal Axes Centrifuges from KMPT. The first antiacid in Hastelloy C22 and the second in AISI316L. The installation was following the turn key formula with all engineering, mechanical, civil and electroinstrumental activities included in the scope of supply.
400.000 litres storage in AISI304. Reverse Osmosys skid unit with capacity 100 mc/h for water production at 5 msiemens conductivity. Distribution piping in 4 inches AISI304 stainless steel.